Situated in Wimbledon, South West London. STN Drylining were asked to carry out all the drylining, plastering, tiling and painting for a new build single dwelling in the heart of Wimbledon.
Co-ordination of trades in small site and managing the works to ensure minimal disruption to existing mews was one of the many challenges we faced. The job was very challenging due to other home owners wanting access to the mews 24/7 meaning we had no where to store our materials, so we had to complete the job in stages, meaning ordering the right amout of materials for that day was highly important. It also meant we didn't have access to a skip so keeping waste down to a minimal amount was critical. As you can see from the photos the job was finished to a high standard.